Construction law EOt

Get Instant Legal Answers - Free AI Legal Help
Join thousands of Australians each month using LawConnect’s AI assistant for fast, personalised legal information. No waiting. No cost. Start now.
Ask Your Question Now

Thalaw

Member
12 January 2020
1
0
1
There is a delay to a construction programme as a result of a client design change changing the footings from limestone to concrete due to the foundations type being discovered at the earth works stage.

The delay occurred 5 days prior to the footings needing to be laid (critical task) but as a result the main contractor needed to engage a concreter to complete the new scope of work. The most readily available concreter was not able to start for at least ten days and therefore the there were 5 days delay to the project.

If the client owns the float in accordance with the contract, is the contractor able to claim the 5 additional days (10-5=5) as an extension of time, given that the delay is as a result of the clients change? Or does he fact that the client owns the float mean that the contractor is responsible for finding a concreter who can complete the works in accordance with the programme?